The lifecycle

Every request that enters an agentsmyth repo walks the same road. Seven phases, in order, with a gate between each one. A phase does not open until the phase before it has left an artifact proving it finished.

The router decides first

Before any phase runs, workflow/router.md classifies the request. Not everything deserves seven gates.

  • Trivial changes skip the loop entirely. A typo does not need a plan.
  • Standard changes run the full loop by default.
  • Complex changes make the full loop mandatory — no shortcuts.

The router also handles resumption. If an artifact chain already exists for the work, it restores context from it instead of starting cold.

The seven phases

PhaseThe agent's jobArtifact
ThinkCapture requirements, classify scope and complexitybrief
PlanArchitecture decisions, implementation plan, verification criteriaplan
BuildImplement against the plan, tracked as it goestask
ReviewCheck the code against the plan's manifest and requirementsreview
TestRun the verification commands, record the evidenceverify
ShipWork the release checklist, sign off risk, record deploy evidenceship
ReflectCapture learnings and open follow-ups after the dust settlesreflect

The gates are real

The router will not let the agent jump the track. Each transition has a condition:

  • Plan runs only when the brief is approved.
  • Build runs only when the plan is approved.
  • Review runs only when the build artifact is complete.
  • Test runs only when review is a pass, or an explicitly accepted pass-with-risk.
  • Ship runs only when verification says ship, or a waiver was accepted with the risk visible.
  • Reflect runs only after Ship.

A blocker anywhere stops forward motion until it is resolved or explicitly waived. Waivers do not make risk disappear. They make it visible and signed.

Here is the gate refusing, concretely. An agent finishes Build and calls Review done. The plan's manifest lists R3, but no changed file in the task artifact cites R3. The coverage check fails the transition. Review does not pass, the gap gets named in writing, and nothing merges on a requirement nobody implemented.

Why the artifact matters more than the phase

The phase is a verb; it happens and it is gone. The artifact is the noun that stays. That is the design center: the phases are how the work gets done, but the artifacts are how the work gets remembered.